Your Machine is Built…Now What?

Blow Molding Know How

Here is what you need to do to get ready for the installation of your new accumulator head machine.

Robert Slawska, President, Proven Technology, Inc.

Share

In my last column, I discussed the steps that you as a blow molder need to take to get ready for your new accumulator-head machine once you’ve ordered it. I called it a pre-installation checklist (see link to article top right).

Now, your machine builder has called you to advise that the machine is done. First, send your molds and material to the machine builder for testing. Once this testing is in process, you will want to put together a “check-out” list before the machine is released to you. See the accompanying checklist for my suggestions.

Once you accept the machine for shipment, note any corrections or missing items that need to be completed. A timetable should be established as to whether the item(s) will be completed prior to shipment or at your plant.

Hold a training session for your personnel during the pre-shipment trials. All aspects of the equipment should be covered during this session. Operators must be provided with in-depth knowledge of the entire blow molding unit. This will include a general machine layout and mechanical features. Pay special attention to the electrical systems, microprocessor controls, and hydraulic components of the machine. These areas are generally problematic for the molders and setup personnel. Many machine controls are numerically represented as a percentage of something. Find out what that “something” is.

After the equipment has been approved for shipment, determine a shipping date. You will require a shipping permit for some trucks for the various states. The appropriate number and type of trucks can be ordered for transportation to your plant. Don’t forget to adequately insure the equipment during shipment to protect against in-transit damage. At this time, the equipment will be disassembled and painted for preparation for shipping. This could take up to four days. Schedule arrival of the equipment with the rigger; this can get expensive, so timing of delivery must be coordinated closely.

Upon completion of the reassembly in your plant, contact the machine manufacturer. Provide advance notice to allow scheduling a service technician to come start up your equipment. Usually the builder will call you to verify that all utilities are hooked up to the machine and it is ready for startup.

Once the service technician arrives in your plant, he or she will perform a complete check of your equipment similar to the pre-shipment testing. The technician will:

•Verify whether any parts are missing or damaged in shipment.

•Check whether machine ground is properly installed.

•Verify incoming voltage on all phases (three).

•Visually check machine to assure proper installation.

•Check for electrical connections.

•Retighten heater bands and straps.

•Check and retighten all bolt connections under proper
temperature.

•Check for proper motor rotations.

•Check water connection to heat exchanger.

•Check air connection.

•Verify hydraulic oil was filtered to 10 micron absolute.

•Verify head and machine are level.

•Check for oil/water leaks.

•Verify molds are installed properly.

•Calibrate clamp zero point with molds mounted.

•Ensure all hydraulic hoses are in proper location and tightened.

•Calibrate tooling (zero and span).

•Set mechanical tooling stops.

•Check for alarm conditions on operator screens.

•Check operation of melt-pressure gage.

•Check operation of rupture-disc limit switch.

•Modify sequence of operation as required.

Upon successful startup and checkout, you will now begin the production cycle on your new equipment. In a perfect world things go well and the equipment runs fine. However, from time to time new components fail during early stages and must be replaced. If you’ve been trained properly you should be able to pinpoint the problem area quickly and solve it. You can minimize downtime by being prepared to face these failures with proper spare parts.

Throughout this entire process your goal is to achieve optimum production in the shortest time. This can be possible with the following considerations:

•Plan early.

•Provide all information quickly to the machine builder.

•Establish what is being built vs. what you want.

•Prepare your plant for new equipment.

•Inform your rigger of all details.

•Get as much training done as possible.

•Do thorough pre-shipment testing.

•Be prepared to receive all of your equipment.

•Plan and be prepared for installation.
 

Process Cooling

Related Content

The Importance of Barrel Heat and Melt Temperature

Barrel temperature may impact melting in the case of very small extruders running very slowly. Otherwise, melting is mainly the result of shear heating of the polymer.

Read More
Tooling

What You Need to Know About Leader Pins and Bushings

There’s a lot more to these humble but essential mold components than you might suspect. Following the author’s tips could save much time, money and frustration.

Read More
best practices

Back to Basics on Mold Venting (Part 1)

Here’s what you need to know to improve the quality of your parts and to protect your molds.

Read More

Fundamentals of Polyethylene – Part 6: PE Performance

Don’t assume you know everything there is to know about PE because it’s been around so long. Here is yet another example of how the performance of PE is influenced by molecular weight and density.

Read More

Read Next

Stretch Blow Molding

Your Pre-Installation Checklist-Part 1

The work really begins after you've ordered your new machine.

Read More
sustainability

For PLASTICS' CEO Seaholm, NPE to Shine Light on Sustainability Successes

With advocacy, communication and sustainability as three main pillars, Seaholm leads a trade association to NPE that ‘is more active today than we have ever been.’    

Read More